This page will be used to show progress in the build. It shows photos and videos of the build
Phase 1: The Slab which includes foundations and the concrete base
The next step was putting in the blocks for foundations. Left is the first a delivery of materials for the concrete foundation footing and slab. Below shows all 42 tons of river sand have been delivered.
The first step “Structure Settings” i.e. planning out where foundations need to be dug. That was carried out on July 24, 2024.
The pictures on the right show the work being carried out
Click to play movie
The second step was digging the trenches for the foundations. This unskilled work was carried out by villagers under supervision by the contractor, starting on August 9, 2024
Cement goes in for the “footings” a concrete base on which the foundation blockwork will be built
Click to play movie
The blockwork for the foundations were put in, showing progress on August 26 on the left. The work was completed, inspected by the District Building Officer (below right) on August 30 and signed off for work to continue to the next stage …. Putting down the concrete slab. For longer versions of the videos see the Exilda’s Angels Facebook page.
Following approval of the foundation blockwork, the trenches needed to be back filled. This is labour intensive, albeit not a skilled task. Some on the western side of the structure were so deep that filling has been a challenge. People from several villages helpedwith this work with each village being allocated a portion of the work.