Building the 3 new Classrooms

This page will be used to show progress in the build. It shows photos and videos of the build

Phase 1: The Slab which includes foundations and the concrete base

 

The next step was putting in the blocks for foundations. Left is the first a delivery of materials for the concrete foundation footing and slab. Below shows all 42 tons of river sand have been delivered.

The first step “Structure Settings” i.e. planning out where foundations need to be dug. That was carried out on July 24, 2024.

The pictures on the right show the work being carried out


Click to play movie

The second step was digging the trenches for the foundations. This unskilled work was carried out by villagers under supervision by the contractor, starting on August  9, 2024

Cement goes in for the “footings” a concrete base on which the foundation blockwork will be built

Click to play movie

The blockwork for the foundations were put in,  showing progress on August 26 on the left. The work was completed, inspected by the District Building Officer (below right) on August 30 and signed off for work to continue to the next stage  …. Putting down the concrete slab.   For longer versions of the videos see the Exilda’s Angels Facebook page.

Following approval of the foundation blockwork, the trenches needed to be back filled. This is labour intensive, albeit not a skilled task. Some on the western side of the structure were so deep that filling has been a challenge. People from several villages helpedwith this work with each village being allocated a portion of the work.

The ladies had a particular way of moving earth

See this video clip on the Exilda’s Angels Facebook group posted 20 September 2024

See this video clip on the Exilda’s Angels Facebook group posted 20 September 2024

Some of the pupils looking at the base of their new classrooms

Before the concrete slab can be laid, the ground that has been backfilled needs to be compacted

See a longer version of this video clip on the Exilda’s Angels Facebook group posted 25 September 2024

See a longer version of this video clip on the Exilda’s Angels Facebook group posted 25 September 2024

The headteacher played his part in the compacting

Making the concrete slab

Finishing off the slab October 5, 2024